If 7 men can do a job in 24 days and 3 men are fired from the job how long will the remaining men take

Respuesta :

mwall62
mwall62 mwall62
  • 02-01-2022

Answer:

36 Days to Do the job

Step-by-step explanation:

Answer Link

Otras preguntas

Write the name of CH3 ----CH2 ---- CH3
Use the features and format of formal letter to write a letter to the chairman of your local government area requesting some social amenities in your area.
my brain hurting can u help
HELP! 7th grade math! GIVE CORRECT ANSWER AND YOU WILL GET BRAINLIEST!!
Select the correct answer. Four-thirds times the sum of a number and 8 is 24. What is the number? A. 40 B. 26 O c. 24 OD. 10
What is potential energy?
Which equation represents "the product of a number and 24 is 72"? 24p-72 24 = 72p (24(72) =p = 72
Please help ASAP!!!!!!
Athena Company's salaried employees earn two weeks of vacation per year. It pays $858,000 in total employee salaries for 52 weeks but its employees work only 50
Find the solution set for this equation. -m2 - 5m=0 Separate the two values with a comma. Enter the correct answer.